Honolulu's new building permit system, HNL Build, launched in August 2025, has cut residential permit wait times significantly while making commercial permits slower. For homeowners and small contractors, the improvement is real. For businesses trying to get construction projects approved, the transition has added time and uncertainty to an already difficult process.

The residential numbers: the median wait for a new residential building permit dropped to 2.5 months through the August-to-April window, a 40 percent improvement over the same period the prior year, when permits took about four months. Alteration permits, which cover the most common homeowner projects, fell from roughly three months to about 40 days. The department processed more than 17,000 permits between August and mid-April, up 40 percent from the prior year's comparable period.

Commercial permits moved the other direction. Under the old POSSE system, the median commercial permit wait was 85 days, just under three months. Under HNL Build, it's risen to about four months, with many commercial projects taking roughly a month longer than before. The 15 largest pending commercial projects submitted after August had a combined value of $138.5 million sitting in the queue.

The department is operating with 20 percent of its 365 positions vacant. That staffing gap means complex commercial applications, which require more human review than residential ones, slow down even when automation handles simpler submissions faster. Fee revenue dropped from $24.6 million to $12.75 million over the period, partly reflecting lower commercial activity and partly the revenue structure tied to larger project types.

DPP officials say the commercial backlog is a known issue under active review. The HNL Build transition cost an estimated $7.3 million. The system is still being refined, and fixing commercial throughput is the next problem to solve.